BetaActiveBatteryPJMLBNL
25 MW storage in Van Buren, MI · In queue since August 2020 · Proposed COD March 2022
25 MW
Capacity
1
Components
Battery
5y 7m
In Queue
System Impact Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 7m
Schedule
50 months past proposed COD
Impact Study25%
Queue EntryAug 31, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-03-01
Project Details
State
MI
County
Van Buren
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Valley 138 kV
Data Source
LBNL