Palomino Solar
BetaActiveSolarPJMLBNL + Live
150 MW generation in Highland, OH · In queue since August 2020 · Proposed COD August 2027
150 MW
Capacity
1
Components
Solar
5y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7 years
Facilities Study50%
Queue EntryAug 31, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-08-15
Project Details
State
OH
County
Highland
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Hillsboro-Middleboro 138 kV
Data Source
LBNL + Live
No news available for this project.