— Project Summary

Queue ID
PJM-AG1-106
Capacity
23 MW
Technology
Solar
Status
active
Location
Northampton, NC
Region
PJM
Developer
IA Status
Feasibility Study

BetaActiveSolarPJMLBNL

23 MW generation in Northampton, NC · In queue since August 2020 · Proposed COD June 2024

23 MW

Capacity

1

Components

Solar

5y 7m

In Queue

Feasibility Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 10m

Schedule

22 months past proposed COD

Feasibility Study13%
Queue EntryAug 28, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-06-01

Project Details

State

NC

County

Northampton

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Thelma 230 kV

Data Source

LBNL