BetaActiveSolarBatteryPJMLBNL
95 MW hybrid in Centre, PA · In queue since August 2020 · Proposed COD August 2023
95 MW
Capacity
1
Components
Solar
5y 7m
In Queue
Feasibility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3 years
Schedule
32 months past proposed COD
Feasibility Study13%
Queue EntryAug 1, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-08-01
Project Details
State
PA
County
Centre
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Philipsburg 115 kV
Data Source
LBNL
No news available for this project.