— Project Summary

Queue ID
PJM-AG1-082
Capacity
20 MW
Technology
Solar+Battery
Status
active
Location
Hertford, NC
Region
PJM
Developer
IA Status
Feasibility Study

BetaActiveSolarBatteryPJMLBNL

20 MW hybrid in Hertford, NC · In queue since July 2020 · Proposed COD December 2021

20 MW

Capacity

1

Components

Solar

5y 8m

In Queue

Feasibility Study

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

1y 5m

Schedule

52 months past proposed COD

Feasibility Study13%
Queue EntryJul 31, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-31

Project Details

State

NC

County

Hertford

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Ahoskie 34.5 kV

Data Source

LBNL

No news available for this project.