20 MW hybrid in Hertford, NC · In queue since July 2020 · Proposed COD December 2021
20 MW
Capacity
1
Components
Solar
5y 8m
In Queue
Feasibility Study
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
1y 5m
Schedule
52 months past proposed COD
Feasibility Study13%
Queue EntryJul 31, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-12-31
Project Details
State
NC
County
Hertford
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Ahoskie 34.5 kV
Data Source
LBNL