BetaActiveSolarPJMLBNL
55 MW generation in Barren, KY · In queue since July 2020 · Proposed COD June 2024
55 MW
Capacity
1
Components
Solar
5y 8m
In Queue
System Impact Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 11m
Schedule
22 months past proposed COD
Impact Study25%
Queue EntryJul 30, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-06-01
Project Details
State
KY
County
Barren
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
Bon Ayr 69 kV
Data Source
LBNL
No news available for this project.