— Project Summary

Queue ID
PJM-AG1-070
Capacity
45 MW
Technology
Solar
Status
active
Location
Barren, KY
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarPJMLBNL

45 MW generation in Barren, KY · In queue since July 2020 · Proposed COD June 2024

45 MW

Capacity

1

Components

Solar

5y 8m

In Queue

System Impact Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 11m

Schedule

22 months past proposed COD

Impact Study25%
Queue EntryJul 30, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-06-01

Project Details

State

KY

County

Barren

Region

PJM

Developer

Utility

EKPC

Entity

PJM

Point of Interconnection

Bon Ayr 69 kV

Data Source

LBNL

No news available for this project.