Bright Mountain Solar
BetaActiveSolarPJMLBNL + Live
80 MW generation in Perry, KY · In queue since July 2020 · Proposed COD January 2027
80 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 6m
Construction75%
Queue EntryJul 30, 2020
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-01-27
Project Details
State
KY
County
Perry
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Bonnyman 69 kV
Data Source
LBNL + Live