Green Meadows Solar — Project Summary

Queue ID
PJM-AG1-054
Capacity
40 MW
Technology
Solar
Status
active
Location
Lawrence, PA
Region
PJM
Developer
IA Status
IA Executed

Green Meadows Solar

BetaActiveSolarPJMLBNL + Live

40 MW generation in Lawrence, PA · In queue since July 2020 · Proposed COD May 2027

40 MW

Capacity

1

Components

Solar

5y 8m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

6y 10m

Construction75%
Queue EntryJul 21, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-05-31

Project Details

State

PA

County

Lawrence

Region

PJM

Developer

Utility

ATSI

Entity

PJM

Point of Interconnection

Potter-Harlan 69 kV

Data Source

LBNL + Live