Sun Chief Solar Farm — Project Summary

Queue ID
PJM-AG1-047
Capacity
100 MW
Technology
Solar
Status
active
Location
Jay, IN
Region
PJM
Developer
IA Status
IA Executed

Sun Chief Solar Farm

BetaActiveSolarPJMLBNL + Live

100 MW generation in Jay, IN · In queue since July 2020 · Proposed COD March 2027

100 MW

Capacity

1

Components

Solar

5y 8m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

6y 8m

Construction75%
Queue EntryJul 13, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-03-31

Project Details

State

IN

County

Jay

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Jay 138 kV

Data Source

LBNL + Live

No news available for this project.