45 MW generation in Lancaster, VA · In queue since June 2020 · Proposed COD December 2027
45 MW
Capacity
1
Components
Solar
5y 9m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 6m
Impact Study25%
Queue EntryJun 16, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
VA
County
Lancaster
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Garner DP-Lancaster 115 kV
Data Source
LBNL + Live
No news available for this project.