— Project Summary

Queue ID
PJM-AG1-038
Capacity
45 MW
Technology
Solar
Status
active
Location
Lancaster, VA
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarPJMLBNL + Live

45 MW generation in Lancaster, VA · In queue since June 2020 · Proposed COD December 2027

45 MW

Capacity

1

Components

Solar

5y 9m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

7y 6m

Impact Study25%
Queue EntryJun 16, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

VA

County

Lancaster

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Garner DP-Lancaster 115 kV

Data Source

LBNL + Live

No news available for this project.