NC3 Ahoskie South Solar Project
BetaActiveSolarBatteryPJMLBNL + Live
5 MW hybrid in Hertford, NC · In queue since June 2020 · Proposed COD August 2027
5 MW
Capacity
1
Components
Solar
5y 9m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 2m
Impact Study25%
Queue EntryJun 16, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-08-29
Project Details
State
NC
County
Hertford
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Ahoskie 34.5 kV
Data Source
LBNL + Live
No news available for this project.