NC3 Ahoskie South Solar Project — Project Summary

Queue ID
PJM-AG1-037
Capacity
5 MW
Technology
Solar+Battery
Status
active
Location
Hertford, NC
Region
PJM
Developer
IA Status
System Impact Study

NC3 Ahoskie South Solar Project

BetaActiveSolarBatteryPJMLBNL + Live

5 MW hybrid in Hertford, NC · In queue since June 2020 · Proposed COD August 2027

5 MW

Capacity

1

Components

Solar

5y 9m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

7y 2m

Impact Study25%
Queue EntryJun 16, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-08-29

Project Details

State

NC

County

Hertford

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Ahoskie 34.5 kV

Data Source

LBNL + Live

No news available for this project.