Harvey Solar I — Project Summary

Queue ID
PJM-AG1-034
Capacity
127.5 MW
Technology
Solar
Status
active
Location
Licking, OH
Region
PJM
Developer
IA Status
Facility Study

Harvey Solar I

BetaActiveSolarPJMLBNL + Live

127.5 MW generation in Licking, OH · In queue since June 2020 · Proposed COD January 2029

127.5 MW

Capacity

1

Components

Solar

5y 9m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

8y 7m

Facilities Study50%
Queue EntryJun 12, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-01-15

Project Details

State

OH

County

Licking

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Centerburg 138 kV

Data Source

LBNL + Live