— Project Summary

Queue ID
PJM-AG1-008
Capacity
126 MW
Technology
Solar
Status
active
Location
Hertford, NC
Region
PJM
Developer
IA Status
Feasibility Study

BetaActiveSolarPJMLBNL

126 MW generation in Hertford, NC · In queue since May 2020 · Proposed COD December 2024

126 MW

Capacity

1

Components

Solar

5y 10m

In Queue

Feasibility Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

4y 7m

Schedule

16 months past proposed COD

Feasibility Study13%
Queue EntryMay 1, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-15

Project Details

State

NC

County

Hertford

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Tunis-Mapleton 115 kV

Data Source

LBNL

No news available for this project.