BetaActiveSolarPJMLBNL
126 MW generation in Hertford, NC · In queue since May 2020 · Proposed COD December 2024
126 MW
Capacity
1
Components
Solar
5y 10m
In Queue
Feasibility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
4y 7m
Schedule
16 months past proposed COD
Feasibility Study13%
Queue EntryMay 1, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-15
Project Details
State
NC
County
Hertford
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Tunis-Mapleton 115 kV
Data Source
LBNL
No news available for this project.