BetaActiveSolarPJMLBNL + Live
9.4 MW generation in Edgecombe, NC · In queue since May 2020 · Proposed COD June 2028
9.4 MW
Capacity
1
Components
Solar
5y 10m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8y 1m
Impact Study25%
Queue EntryMay 1, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-01
Project Details
State
NC
County
Edgecombe
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Tar River 12.5 kV
Data Source
LBNL + Live
No news available for this project.