— Project Summary

Queue ID
PJM-AG1-007
Capacity
9.4 MW
Technology
Solar
Status
active
Location
Edgecombe, NC
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarPJMLBNL + Live

9.4 MW generation in Edgecombe, NC · In queue since May 2020 · Proposed COD June 2028

9.4 MW

Capacity

1

Components

Solar

5y 10m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

8y 1m

Impact Study25%
Queue EntryMay 1, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-01

Project Details

State

NC

County

Edgecombe

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Tar River 12.5 kV

Data Source

LBNL + Live