BetaActiveBatteryPJMLBNL
200 MW storage in Cook, IL · In queue since March 2020 · Proposed COD May 2024
200 MW
Capacity
1
Components
Battery
6 years
In Queue
Feasibility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
4y 2m
Schedule
22 months past proposed COD
Feasibility Study13%
Queue EntryMar 31, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-05-31
Project Details
State
IL
County
Cook
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Burnham 138kV
Data Source
LBNL
No news available for this project.