— Project Summary

Queue ID
PJM-AF2-441
Capacity
200 MW
Technology
Battery
Status
active
Location
Cook, IL
Region
PJM
Developer
IA Status
Feasibility Study

BetaActiveBatteryPJMLBNL

200 MW storage in Cook, IL · In queue since March 2020 · Proposed COD May 2024

200 MW

Capacity

1

Components

Battery

6 years

In Queue

Feasibility Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

4y 2m

Schedule

22 months past proposed COD

Feasibility Study13%
Queue EntryMar 31, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-05-31

Project Details

State

IL

County

Cook

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Burnham 138kV

Data Source

LBNL

No news available for this project.