Frosty Valley Energy Center
BetaActiveSolarPJMLBNL + Live
20 MW generation in Anne Arundel, MD · In queue since March 2020 · Proposed COD January 2027
20 MW
Capacity
1
Components
Solar
6 years
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 10m
Construction75%
Queue EntryMar 31, 2020
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-01-15
Project Details
State
MD
County
Anne Arundel
Region
PJM
Developer
—
Utility
PPL
Entity
PJM
Point of Interconnection
Columbia-Geisinger Tap #1 69 kV
Data Source
LBNL + Live
No news available for this project.