Two Rivers Storage
BetaActiveBatteryPJMLBNL + Live
150 MW storage in Hudson, NJ · In queue since March 2020 · Proposed COD May 2028
150 MW
Capacity
1
Components
Battery
6 years
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8y 2m
Construction75%
Queue EntryMar 31, 2020
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2028-05-30
Project Details
State
NJ
County
Hudson
Region
PJM
Developer
—
Utility
PSEG
Entity
PJM
Point of Interconnection
Bergen 138 kV
Data Source
LBNL + Live
News & Articles (1)Beta