RHC Solar
BetaActiveSolarBatteryPJMLBNL + Live
3.9 MW hybrid in Somerset, MD · In queue since April 2020 · Proposed COD December 2024
3.9 MW
Capacity
1
Components
Solar
5y 11m
In Queue
System Impact Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
4y 8m
Schedule
16 months past proposed COD
Impact Study25%
Queue EntryApr 1, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-01
Project Details
State
MD
County
Somerset
Region
PJM
Developer
—
Utility
DPL
Entity
PJM
Point of Interconnection
Princess Anne 25 kV
Data Source
LBNL + Live
No news available for this project.