GGC Solar
BetaActiveSolarBatteryPJMLBNL + Live
2.65 MW hybrid in Dorchester, MD · In queue since March 2020 · Proposed COD March 2024
2.65 MW
Capacity
1
Components
Solar
6 years
In Queue
System Impact Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
4 years
Schedule
24 months past proposed COD
Impact Study25%
Queue EntryMar 31, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-03-31
Project Details
State
MD
County
Dorchester
Region
PJM
Developer
—
Utility
DPL
Entity
PJM
Point of Interconnection
Cambridge 12 kV
Data Source
LBNL + Live