Red Maple Solar
94.9 MW generation in Adams, IL · In queue since March 2020 · Proposed COD February 2028
94.9 MW
Capacity
1
Components
Solar
6 years
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
7y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-02-07
State
IL
County
Adams
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Crego Rd 138 kV
Data Source
LBNL + Live
Invenergy, Verizon Expand PPAs for Solar Power
Energy major Invenergy and telecom company Verizon are moving forward with power purchase agreements (PPAs) involving 640 MW of solar energy from projects...
Invenergy, Verizon Expand PPAs for Solar Power
Energy major Invenergy and telecom company Verizon are moving forward with power purchase agreements (PPAs) involving 640 MW of solar energy from projects...
Invenergy, Verizon Expand PPAs for Solar Power
Energy major Invenergy and telecom company Verizon are moving forward with power purchase agreements (PPAs) involving 640 MW of solar energy from projects...
Invenergy, Verizon Expand PPAs for Solar Power
Energy major Invenergy and telecom company Verizon are moving forward with power purchase agreements (PPAs) involving 640 MW of solar energy from projects...
Last updated 2026-03-26