— Project Summary

Queue ID
PJM-AF2-365
Capacity
50 MW
Technology
Solar
Status
active
Location
Hart, KY
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarPJMLBNL

50 MW generation in Hart, KY · In queue since March 2020 · Proposed COD December 2022

50 MW

Capacity

1

Components

Solar

6 years

In Queue

System Impact Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

2y 9m

Schedule

39 months past proposed COD

Impact Study25%
Queue EntryMar 31, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-31

Project Details

State

KY

County

Hart

Region

PJM

Developer

Utility

EKPC

Entity

PJM

Point of Interconnection

Munfordville KU Tap-Horse Cave Jct. 69 kV

Data Source

LBNL

No news available for this project.