— Project Summary

Queue ID
PJM-AF2-359
Capacity
125 MW
Technology
Solar
Status
active
Location
Laporte, IN
Region
PJM
Developer
IA Status
Facility Study

BetaActiveSolarPJMLBNL + Live

125 MW generation in Laporte, IN · In queue since March 2020 · Proposed COD December 2027

125 MW

Capacity

1

Components

Solar

6 years

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

7y 9m

Facilities Study50%
Queue EntryMar 31, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Project Details

State

IN

County

Laporte

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Olive-University Park 345 kV

Data Source

LBNL + Live

No news available for this project.