BetaActiveSolarPJMLBNL + Live
125 MW generation in Laporte, IN · In queue since March 2020 · Proposed COD December 2027
125 MW
Capacity
1
Components
Solar
6 years
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 9m
Facilities Study50%
Queue EntryMar 31, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
IN
County
Laporte
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Olive-University Park 345 kV
Data Source
LBNL + Live
No news available for this project.