CPV Backbone Solar — Project Summary

Queue ID
PJM-AF2-356
Capacity
175 MW
Technology
Solar
Status
active
Location
Garrett, MD
Region
PJM
Developer
IA Status
IA Executed

CPV Backbone Solar

BetaActiveSolarPJMLBNL + Live

175 MW generation in Garrett, MD · In queue since March 2020 · Proposed COD March 2026

175 MW

Capacity

1

Components

Solar

6 years

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

6 years

Schedule

0 months past proposed COD

Construction75%
Queue EntryMar 31, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-03-15

Project Details

State

MD

County

Garrett

Region

PJM

Developer

Utility

APS

Entity

PJM

Point of Interconnection

Albright-Mt. Zion 138 kV

Data Source

LBNL + Live