Washington Solar PH II
BetaActiveSolarPJMLBNL + Live
11 MW generation in Warren, NJ · In queue since March 2020 · Proposed COD August 2025
11 MW
Capacity
1
Components
Solar
6 years
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
5y 5m
Schedule
7 months past proposed COD
Construction75%
Queue EntryMar 31, 2020
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-08-29
Project Details
State
NJ
County
Warren
Region
PJM
Developer
—
Utility
JCPL
Entity
PJM
Point of Interconnection
Washington 34.5 kV II
Data Source
LBNL + Live
No news available for this project.