SBC Solar — Project Summary

Queue ID
PJM-AF2-325
Capacity
10 MW
Technology
Solar+Battery
Status
active
Location
Dorchester, MD
Region
PJM
Developer
IA Status
System Impact Study

SBC Solar

BetaActiveSolarBatteryPJMLBNL + Live

10 MW hybrid in Dorchester, MD · In queue since March 2020 · Proposed COD December 2027

10 MW

Capacity

1

Components

Solar

6 years

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

7y 9m

Impact Study25%
Queue EntryMar 30, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

MD

County

Dorchester

Region

PJM

Developer

Utility

DPL

Entity

PJM

Point of Interconnection

Jacktown 12 kV

Data Source

LBNL + Live

No news available for this project.