BetaActiveBatteryPJMLBNL
50 MW storage in Lasalle, IL · In queue since March 2020 · Proposed COD October 2023
50 MW
Capacity
1
Components
Battery
6 years
In Queue
System Impact Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 7m
Schedule
29 months past proposed COD
Impact Study25%
Queue EntryMar 30, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-10-31
Project Details
State
IL
County
Lasalle
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Katydid Road 345 kV
Data Source
LBNL
No news available for this project.