Nicholas Solar
100 MW generation in Nicholas, WV · In queue since March 2020 · Proposed COD February 2029
100 MW
Capacity
1
Components
Solar
6 years
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
8y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2029-02-28
State
WV
County
Nicholas
Region
PJM
Developer
—
Utility
APS
Entity
PJM
Point of Interconnection
Gilboa-Jones Branch 138 kV
Data Source
LBNL + Live
Alliant Energy’s Linn County solar field now operational
What Alliant Energy calls the largest solar field in Iowa is now operational in Linn County, and is getting a new name.
Alliant Energy’s Linn County solar field now operational
What Alliant Energy calls the largest solar field in Iowa is now operational in Linn County, and is getting a new name.
Alliant Energy’s Linn County solar field now operational
What Alliant Energy calls the largest solar field in Iowa is now operational in Linn County, and is getting a new name.
Alliant Energy’s Linn County solar field now operational
What Alliant Energy calls the largest solar field in Iowa is now operational in Linn County, and is getting a new name.
Last updated 2026-03-26