— Project Summary

Queue ID
PJM-AF2-307
Capacity
64.2 MW
Technology
Solar
Status
active
Location
Bath, KY
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarPJMLBNL

64.2 MW generation in Bath, KY · In queue since March 2020 · Proposed COD September 2023

64.2 MW

Capacity

1

Components

Solar

6 years

In Queue

System Impact Study

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 6m

Schedule

31 months past proposed COD

Impact Study25%
Queue EntryMar 30, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-09-01

Project Details

State

KY

County

Bath

Region

PJM

Developer

Utility

EKPC

Entity

PJM

Point of Interconnection

Hope-Belvins Valley Tap 69 kV

Data Source

LBNL