BetaActiveSolarBatteryPJMLBNL + Live
89 MW hybrid in Surry, VA · In queue since March 2020 · Proposed COD September 2028
89 MW
Capacity
1
Components
Solar
6 years
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8y 6m
Facilities Study50%
Queue EntryMar 30, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-01
Project Details
State
VA
County
Surry
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Surry-Hopewell 230 kV
Data Source
LBNL + Live
No news available for this project.