Jarratt Energy Facility 2
BetaActiveSolarPJMLBNL
18 MW generation in Greensville, VA · In queue since March 2020 · Proposed COD December 2022
18 MW
Capacity
1
Components
Solar
6 years
In Queue
System Impact Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
2y 9m
Schedule
40 months past proposed COD
Impact Study25%
Queue EntryMar 30, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-12
Project Details
State
VA
County
Greensville
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Fields 34.5 kV
Data Source
LBNL
No news available for this project.