Jarratt Energy Facility 2 — Project Summary

Queue ID
PJM-AF2-299
Capacity
18 MW
Technology
Solar
Status
active
Location
Greensville, VA
Region
PJM
Developer
IA Status
System Impact Study

Jarratt Energy Facility 2

BetaActiveSolarPJMLBNL

18 MW generation in Greensville, VA · In queue since March 2020 · Proposed COD December 2022

18 MW

Capacity

1

Components

Solar

6 years

In Queue

System Impact Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

2y 9m

Schedule

40 months past proposed COD

Impact Study25%
Queue EntryMar 30, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-12

Project Details

State

VA

County

Greensville

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Fields 34.5 kV

Data Source

LBNL

No news available for this project.