— Project Summary

Queue ID
PJM-AF2-298
Capacity
49.9 MW
Technology
Solar
Status
active
Location
Montgomery, OH
Region
PJM
Developer
IA Status
Facility Study

BetaActiveSolarPJMLBNL + Live

49.9 MW generation in Montgomery, OH · In queue since March 2020 · Proposed COD January 2028

49.9 MW

Capacity

1

Components

Solar

6 years

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

7y 10m

Facilities Study50%
Queue EntryMar 30, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-01-02

Project Details

State

OH

County

Montgomery

Region

PJM

Developer

Utility

Dayton

Entity

PJM

Point of Interconnection

Crown-New Lebanon 69 kV

Data Source

LBNL + Live

No news available for this project.