BetaActiveSolarPJMLBNL
20 MW generation in Clearfield, PA · In queue since March 2020 · Proposed COD October 2021
20 MW
Capacity
1
Components
Solar
6 years
In Queue
System Impact Study
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
1y 7m
Schedule
55 months past proposed COD
Impact Study25%
Queue EntryMar 28, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-10-01
Project Details
State
PA
County
Clearfield
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Madera 34.5 kV
Data Source
LBNL
No news available for this project.