BetaSuspendedSolarPJMLBNL + Live
17 MW generation in Wayne, PA · In queue since March 2020 · Proposed COD March 2025
17 MW
Capacity
1
Components
Solar
6 years
In Queue
System Impact Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
5 years
Suspended25%
Queue EntryMar 29, 2020
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-03-31
Project Details
State
PA
County
Wayne
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Thompson 34.5 kV
Data Source
LBNL + Live
No news available for this project.