New Haven Solar — Project Summary

Queue ID
PJM-AF2-291
Capacity
100 MW
Technology
Solar
Status
active
Location
Mason, WV
Region
PJM
Developer
IA Status
IA Executed

New Haven Solar

BetaActiveSolarPJMLBNL + Live

100 MW generation in Mason, WV · In queue since March 2020 · Proposed COD January 2028

100 MW

Capacity

1

Components

Solar

6 years

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

7y 10m

Construction75%
Queue EntryMar 28, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-01-31

Project Details

State

WV

County

Mason

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Sporn South-Leon 138 kV

Data Source

LBNL + Live

No news available for this project.