Twin Groves Storage I — Project Summary

Queue ID
PJM-AF2-252
Capacity
50 MW
Technology
Battery
Status
active
Location
Mclean, IL
Region
PJM
Developer
IA Status
IA Executed

Twin Groves Storage I

BetaActiveBatteryPJMLBNL + Live

50 MW storage in Mclean, IL · In queue since March 2020 · Proposed COD January 2028

50 MW

Capacity

1

Components

Battery

6 years

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

7y 10m

Construction75%
Queue EntryMar 27, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2028-01-28

Project Details

State

IL

County

Mclean

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Blue Mound 345 kV

Data Source

LBNL + Live

No news available for this project.