Farmers Valley Solar
BetaActiveSolarPJMLBNL + Live
20 MW generation in Bradford, PA · In queue since March 2020 · Proposed COD July 2028
20 MW
Capacity
1
Components
Solar
6 years
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8y 4m
Construction75%
Queue EntryMar 26, 2020
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-07-31
Project Details
State
PA
County
Bradford
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Mansfield-South Troy 34.5 kV
Data Source
LBNL + Live
No news available for this project.