Farmers Valley Solar — Project Summary

Queue ID
PJM-AF2-238
Capacity
20 MW
Technology
Solar
Status
active
Location
Bradford, PA
Region
PJM
Developer
IA Status
IA Executed

Farmers Valley Solar

BetaActiveSolarPJMLBNL + Live

20 MW generation in Bradford, PA · In queue since March 2020 · Proposed COD July 2028

20 MW

Capacity

1

Components

Solar

6 years

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

8y 4m

Construction75%
Queue EntryMar 26, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-07-31

Project Details

State

PA

County

Bradford

Region

PJM

Developer

Utility

PENELEC

Entity

PJM

Point of Interconnection

Mansfield-South Troy 34.5 kV

Data Source

LBNL + Live

No news available for this project.