Gobbler Knob — Project Summary

Queue ID
PJM-AF2-229
Capacity
20 MW
Technology
Solar
Status
active
Location
Cumberland, PA
Region
PJM
Developer
IA Status
IA Executed

Gobbler Knob

BetaActiveSolarPJMLBNL + Live

20 MW generation in Cumberland, PA · In queue since March 2020 · Proposed COD November 2027

20 MW

Capacity

1

Components

Solar

6 years

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

7y 8m

Construction75%
Queue EntryMar 26, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-11-30

Project Details

State

PA

County

Cumberland

Region

PJM

Developer

Utility

PENELEC

Entity

PJM

Point of Interconnection

Roxbury 23 kV

Data Source

LBNL + Live

No news available for this project.