— Project Summary

Queue ID
PJM-AF2-225
Capacity
150 MW
Technology
Solar
Status
active
Location
Mclean, IL
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarPJMLBNL

150 MW generation in Mclean, IL · In queue since March 2020 · Proposed COD October 2022

150 MW

Capacity

1

Components

Solar

6 years

In Queue

System Impact Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

2y 7m

Schedule

41 months past proposed COD

Impact Study25%
Queue EntryMar 26, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-10-31

Project Details

State

IL

County

Mclean

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

McLean 345 kV

Data Source

LBNL

No news available for this project.