BetaActiveSolarPJMLBNL
167 MW generation in Charlotte, VA · In queue since March 2020 · Proposed COD May 2023
167 MW
Capacity
1
Components
Solar
6 years
In Queue
System Impact Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 2m
Schedule
34 months past proposed COD
Impact Study25%
Queue EntryMar 25, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-05-31
Project Details
State
VA
County
Charlotte
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Madisonville DP-Twitty's Creek 115 kV
Data Source
LBNL
No news available for this project.