Barbertown Solar — Project Summary

Queue ID
PJM-AF2-192
Capacity
7 MW
Technology
Solar
Status
suspended
Location
Hunterdon, NJ
Region
PJM
Developer
IA Status
IA Executed

Barbertown Solar

BetaSuspendedSolarPJMLBNL + Live

7 MW generation in Hunterdon, NJ · In queue since March 2020 · Proposed COD June 2026

7 MW

Capacity

1

Components

Solar

6 years

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

6y 3m

Suspended75%
Queue EntryMar 23, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-06-30

Project Details

State

NJ

County

Hunterdon

Region

PJM

Developer

Utility

JCPL

Entity

PJM

Point of Interconnection

Frenchtown Solar-West Flemington 34.5 kV

Data Source

LBNL + Live

No news available for this project.