Barbertown Solar
BetaSuspendedSolarPJMLBNL + Live
7 MW generation in Hunterdon, NJ · In queue since March 2020 · Proposed COD June 2026
7 MW
Capacity
1
Components
Solar
6 years
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
6y 3m
Suspended75%
Queue EntryMar 23, 2020
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-06-30
Project Details
State
NJ
County
Hunterdon
Region
PJM
Developer
—
Utility
JCPL
Entity
PJM
Point of Interconnection
Frenchtown Solar-West Flemington 34.5 kV
Data Source
LBNL + Live
No news available for this project.