300 MW generation in Lee, IL · In queue since March 2020 · Proposed COD December 2022
300 MW
Capacity
1
Components
Solar
6 years
In Queue
Feasibility Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
2y 9m
Schedule
40 months past proposed COD
Feasibility Study13%
Queue EntryMar 21, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-01
Project Details
State
IL
County
Lee
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Nelson-Lee County 345 kV II
Data Source
LBNL
No news available for this project.