200 MW generation in Blackford, IN · In queue since March 2020 · Proposed COD October 2023
200 MW
Capacity
1
Components
Wind
6 years
In Queue
System Impact Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 7m
Schedule
29 months past proposed COD
Impact Study25%
Queue EntryMar 20, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-10-31
Project Details
State
IN
County
Blackford
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Sorenson-DeSoto #2 345 kV
Data Source
LBNL