— Project Summary

Queue ID
PJM-AF2-143
Capacity
150 MW
Technology
Solar
Status
active
Location
Lasalle, IL
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarPJMLBNL

150 MW generation in Lasalle, IL · In queue since March 2020 · Proposed COD December 2023

150 MW

Capacity

1

Components

Solar

6 years

In Queue

System Impact Study

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 9m

Schedule

27 months past proposed COD

Impact Study25%
Queue EntryMar 12, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-31

Project Details

State

IL

County

Lasalle

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Powerton-Nevada 345 kV

Data Source

LBNL

No news available for this project.