— Project Summary

Queue ID
PJM-AF2-126
Capacity
12 MW
Technology
Solar
Status
active
Location
Wood, OH
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarPJMLBNL

12 MW generation in Wood, OH · In queue since February 2020 · Proposed COD December 2021

12 MW

Capacity

1

Components

Solar

6y 1m

In Queue

System Impact Study

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

1y 10m

Schedule

52 months past proposed COD

Impact Study25%
Queue EntryFeb 28, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-31

Project Details

State

OH

County

Wood

Region

PJM

Developer

Utility

ATSI

Entity

PJM

Point of Interconnection

Weston 69 kV II

Data Source

LBNL

No news available for this project.