Union Ridge Solar — Project Summary

Queue ID
PJM-AF2-122
Capacity
107.7 MW
Technology
Solar
Status
active
Location
Licking, OH
Region
PJM
Developer
IA Status
IA Executed

Union Ridge Solar

BetaActiveSolarPJMLBNL + Live

107.7 MW generation in Licking, OH · In queue since February 2020 · Proposed COD January 2026

107.7 MW

Capacity

1

Components

Solar

6y 1m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

5y 11m

Schedule

2 months past proposed COD

Construction75%
Queue EntryFeb 29, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-01-31

Project Details

State

OH

County

Licking

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Kirk 138 kV

Data Source

LBNL + Live