BetaActiveSolarPJMLBNL
62 MW generation in Richmond, VA · In queue since February 2020 · Proposed COD December 2023
62 MW
Capacity
1
Components
Solar
6y 1m
In Queue
System Impact Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 10m
Schedule
28 months past proposed COD
Impact Study25%
Queue EntryFeb 28, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-01
Project Details
State
VA
County
Richmond
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Garner-Northern Neck 115 kV
Data Source
LBNL