250 MW generation in Mason, KY · In queue since February 2020 · Proposed COD December 2023
250 MW
Capacity
1
Components
Solar
6y 1m
In Queue
System Impact Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 10m
Schedule
27 months past proposed COD
Impact Study25%
Queue EntryFeb 28, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
KY
County
Mason
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
North Clark-Spurlock 345 kV
Data Source
LBNL