BetaActiveSolarPJMLBNL + Live
150 MW generation in Pulaski, VA · In queue since January 2020 · Proposed COD February 2028
150 MW
Capacity
1
Components
Solar
6y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8y 1m
Facilities Study50%
Queue EntryJan 31, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-02-28
Project Details
State
VA
County
Pulaski
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Hazel Hollow-Glen Lyn #1 138 kV
Data Source
LBNL + Live
No news available for this project.