BetaActiveSolarPJMLBNL
144 MW generation in Kankakee, IL · In queue since February 2020 · Proposed COD May 2021
144 MW
Capacity
1
Components
Solar
6y 1m
In Queue
System Impact Study
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
1y 3m
Schedule
59 months past proposed COD
Impact Study25%
Queue EntryFeb 13, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-05-31
Project Details
State
IL
County
Kankakee
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Davis Creek 138 kV
Data Source
LBNL
No news available for this project.